[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939276,606,1,"单选题","根据《计价规范》的规定，下列计日工生效原则的表述，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","其价款按已标价工程量清单中的计日工计价项目及其单价计算",true,{"key":16,"text":17,"correct":18},"B","承包人应在实施过程中，每 3 天提报及有关凭证，报送监理人审查",false,{"key":20,"text":21,"correct":18},"C","监理人通知承包人以计日工方式实施的零星工作，承包人应予执行",{"key":23,"text":24,"correct":18},"D","按照合理的成本与利润构成的原则，由合同当事人确定计日工的单价","本题考查的是计日工引起的合同价款调整。选项 B 错误，采用计日工计价的任何一项工作，承包人应在该项工作实施过程中，每天提交以下报表和有关凭证报送监理人审查；选项 C 错误，根据《计价规范》的规定，发包人通知承包人以计日工方式实施的零星工作，承包人应予执行；选项 D 错误，选项 D 适用前提是已标价工程量清单或预算书中无相应计日工单价时。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]