[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939271":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939271,606,1,"单选题","某工程在施工过程中，因不可抗力造成在建工程损失 26 万元，承包人受伤人员医药费、 补偿金 4 万元，施工机具损坏损失 12 万元，施工机具闲置、施工人员窝工损失 5 万元，工程清 理、修复费用 3 万元。承包人及时向项目监理机构提出了索赔申请。项目监理机构应批准的补偿金额为( )元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","29",true,{"key":20,"text":21,"correct":14},"C","24",{"key":23,"text":24,"correct":14},"D","50","项目监理机构应批准的补偿金额：26+3.5=29.5 万元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]