[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939270":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939270,606,2,"多选题","根据《建设工程工程量清单计价规范》GB50500-2013 规定，工程发包时，招标人压缩的 工期天数不得超过定额工期的 20%，超过者应增加赶工费用。赶工费用主要包括( )。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","人工费的增加",true,{"key":16,"text":17,"correct":14},"B","材料费的增加",{"key":19,"text":20,"correct":14},"C","机械费的增加",{"key":22,"text":23,"correct":24},"D","管理费的增加",false,{"key":26,"text":27,"correct":24},"E","利润的增加","ABC","赶工费用主要包括：①人工费的增加；②材料费的增加；③机械费的增加。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]