[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939251":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939251,606,2,"多选题","下列产生工程项目投资偏差的原因中，属于业主原因的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设手续不全",true,{"key":16,"text":17,"correct":18},"B","施工方案不当",false,{"key":20,"text":21,"correct":14},"C","组织不落实",{"key":23,"text":24,"correct":18},"D","设计错误",{"key":26,"text":27,"correct":14},"E","协调不佳","ACE","本题考查的是投资偏差分析。业主原因：需求变更、投资规划不当、组织不落实、建设手续不全、协调不佳、未及时提供场地等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]