[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939248":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939248,606,2,"多选题","措施项目费的计算方法中的参数法计价适用于的措施项目包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","混凝土模板",false,{"key":16,"text":17,"correct":18},"B","夜间施工费",true,{"key":20,"text":21,"correct":18},"C","二次搬运费",{"key":23,"text":24,"correct":18},"D","冬雨期施工",{"key":26,"text":27,"correct":14},"E","脚手架施工","BCD","本题考查的是工程量清单计价。措施项目费的计算方法有：综合单价法、参数法计价、分包法计价。综合单价法适用于可以计算工程量的措施项目，主要是指一些与工程实体有紧密联系的项目，如混凝土模板、脚手架、垂直运输等。 参数法计价简单明了，但最大的难点是公式的科学性、准确性难以把握。这种方法主要适用于施工过程中必须发生，但在投标时很难具体分项预测，又无法单独列出项目内容的措施项目。如夜间施工费、二次搬运费、冬雨期施工的计价均可以采用该方法。分包法计价是在分包价格的基础上增加投标人的管理费及风险费进行计价的方法，这种方法适合可以分包的独立项目，如室内空气污染测试等",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]