[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939242,606,1,"单选题","有关质量保证金的说法，不正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人应从第一个付款周期开始扣留",false,{"key":16,"text":17,"correct":18},"B","计算额度包括预付款的支付、扣回",true,{"key":20,"text":21,"correct":14},"C","期限为缺陷责任期满",{"key":23,"text":24,"correct":14},"D","承包人没有完成缺陷责任的，发包人有权扣留相应金额","本题考查的是合同价款支付。质量保证金的计算额度不包括预付款的支付、扣回以及价格调整的金额",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]