[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939240,606,1,"单选题","时间－投资累计曲线（S 形曲线），当所有工作都按最迟开始时间开始，那么对（ ）有利。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","保证质量",false,{"key":16,"text":17,"correct":14},"B","加快进度",{"key":19,"text":20,"correct":14},"C","安全管理",{"key":22,"text":23,"correct":24},"D","节约贷款利息",true,"本题考查的是资金使用计划的编制。在时间－投资累计曲线中，当所有工作都按最迟开始时间开始，则对节约发包人的建设资金贷款利息是有利的。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]