[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939239,606,1,"单选题","在编制招标控制价时，计日工中的材料价格应按（ ）计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程造价管理机构发布的单价",true,{"key":16,"text":17,"correct":18},"B","清单中列出的单价",false,{"key":20,"text":21,"correct":18},"C","市场调查确定的单价",{"key":23,"text":24,"correct":18},"D","清单中列出的金额","本题考查的是招标控制价的编制。在编制招标控制价时，计日工中的材料单价应按工程造价管理机构发布的工程造价信息中的材料单价计算；若未公布，则按市场调查确定。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]