[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939237,606,1,"单选题","暂估材料或工程设备的单价确定后，在综合单价中只应取代原暂估单价。则下列不属于暂估单价内涵的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","材料费",false,{"key":16,"text":17,"correct":14},"B","企业管理费",{"key":19,"text":20,"correct":14},"C","利润",{"key":22,"text":23,"correct":24},"D","规费",true,"本题考查的是暂估价。暂估材料或工程设备的单价确定后，在综合单价中只应取代原暂估单价，不应再在综合单价中涉及企业管理费或利润等其他费的变动。故可以认为，暂估材料单价或工程设备单价包括管理费和利润。但不包括规费和税金。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]