[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939236,606,1,"单选题","根据《建设工程工程量清单计价规范》，下列关于项目特征不符引起合同价款调整的表述，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目特征是构成清单项目价值的本质特征，单价的高低与其联系不大",true,{"key":16,"text":17,"correct":18},"B","发包人在招标工程量清单中对项目特征的描述，应被认为是准确的和全面的",false,{"key":20,"text":21,"correct":18},"C","当项目特征变化后，发承包双方应按实际施工的项目特征重新确定综合单价",{"key":23,"text":24,"correct":18},"D","承包人应按照发包人提供的招标工程量清单，根据其项目特征描述的内容及有关要求实施合同工程，直到项目被改变为止","本题考查的是项目特征不符引起的合同价款调整。选项 A 错误，项目特征是构成清单项目价值的本质特征，单价的高低与其具有必然的联系。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]