[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939235":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939235,606,1,"单选题","某施工企业进行土方开挖工程，按合同约定 3 月份的计划工作量为 2400m3，计划单价是 12 元\u002Fm3；到月底检查时，工程师确认承包商完成的工程量为 2000m3，实际单价为 15 元\u002Fm3。则该工程的进度偏差（SV）和进度绩效指数（SPI）分别为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","-4800 元；0.67",false,{"key":16,"text":17,"correct":18},"B","-4800 元；0.83",true,{"key":20,"text":21,"correct":14},"C","-6000 元；0.80",{"key":23,"text":24,"correct":14},"D","-12000 元；0.83","本题考查的是投资偏差分析。计算过程如下：进度偏差（SV）＝已完工作预算投资－计划工作预算投资＝2000×12－2400×12＝-4800（元）；进度绩效指数（SPI）＝已完工作预算投资\u002F计划工作预算投资＝2000×12\u002F（2400×12）＝0.83。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]