[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939234":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939234,606,1,"单选题","某工程 10 月份 BCWS 为 50 万元，BCWP 为 45 万元，ACWP 为 48 万元，该工程 10 月底施工成本偏差和进度偏差分别是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","成本超支 3 万元，进度拖延 5 万元",true,{"key":16,"text":17,"correct":18},"B","成本超支 3 万元，进度拖延 3 万元",false,{"key":20,"text":21,"correct":18},"C","成本节约 2 万元，进度提前 5 万元",{"key":23,"text":24,"correct":18},"D","成本节约 2 万元，进度提前 3 万元","本题考查的是投资偏差分析。投资偏差（CV）=已完工作预算投资－已完工作实际投资=45－48=－3（万元），超支 3 万元；进度偏差（SV）=已完工作预算投资－计划工作预算投资=45－50=－5（万元），进度拖延 5 万元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]