[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939232,606,1,"单选题","根据《计价规范》的规定，承包人应发包人的要求，采取加快工程进度的措施，使合同工程工期缩短产生的，应由发包人支付的费用，该费用属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","提前竣工（赶工）费",true,{"key":16,"text":17,"correct":18},"B","施工索赔",false,{"key":20,"text":21,"correct":18},"C","误期赔偿费",{"key":23,"text":24,"correct":18},"D","暂列金额","本题考查的是提前竣工引起的合同价款调整。工程实施过程中，发包人要求合同工程提前竣工的，应征得承包人同意后与承包人商定采取加快工程进度的措施，并应修订合同工程进度计划。发包人应承担承包人由此增加的提前竣工（赶工补偿）费用。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]