[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939230,606,1,"单选题","2018 年 6 月，实际完成的某工程基准日期的价格为 2000 万元。价格调整公式中的固定系数为 0.3，对比基准日前的相关成本要素，水泥的价格指数上升了 30%，水泥的费用占合同调值部分的 40%，其它成本要素的价格均未发生变化。则 2017 年 3 月，应调整的合同价的差额为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","84",false,{"key":16,"text":17,"correct":18},"B","168",true,{"key":20,"text":21,"correct":14},"C","728",{"key":23,"text":24,"correct":14},"D","1328","本题考查的是市场价格波动引起的合同价款调整。在需要调价因素的种类不多、比重较大时，根据调值公式，则有调值后的合同价款差额=2000×［（0.3＋0.7×0.4×130%\u002F100%＋0.7×0.6×1）-1］=168（万元）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]