[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939219":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939219,606,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），若合同未约定，当工程量清单项目的清单工程量偏差在（ ）以内时，其综合单价不作调整，执行清单原有的综合单价。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","10%",{"key":19,"text":20,"correct":21},"C","15%",true,{"key":23,"text":24,"correct":14},"D","20%","本题考查的是工程量偏差。根据“13规范”规定，若合同未约定，当工程量清单项目的清单工程量偏差在15%以内时，其综合单价不作调整。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]