[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939218,606,1,"单选题","在合同价款调整中，不能预见、不可避免、不能克服的客观情况是指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不可抗力",true,{"key":16,"text":17,"correct":18},"B","暂估价",false,{"key":20,"text":21,"correct":18},"C","暂列金额",{"key":23,"text":24,"correct":18},"D","双方约定的其他调整事项","本题考查的是不可抗力。在合同价款调整中，不能预见、不可避免、不能克服的客观情况是指不可抗力。而且，其应当按照签约双方各自损失，各自承担的原则进行处理。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]