[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939214":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939214,606,1,"单选题","某工程采用的 C20 预拌混凝土由承包人提供，合同约定风险系数 5%，基准单价为 310 元 \u002Fm3，投标单价为 308 元\u002Fm3，在施工期间，采购混凝土时单价为 327 元\u002Fm3。合同约定的材料单 价调整后为( )元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","309.50",true,{"key":16,"text":17,"correct":18},"B","319.50",false,{"key":20,"text":21,"correct":18},"C","209.50",{"key":23,"text":24,"correct":18},"D","305.50","涨幅=【实际价格 \u002F max（基准价格；投标单价）-1】＞5%时： 调整后的价格＝投标单价 ＋【max（基准价格和投标单价）×（涨幅-5%）】 跌幅=【1-实际价格 \u002F min（基准价格；投标单价）】＞5%时： 调整后的价格＝投标单价 －【min（基准价格和投标单价）×（跌幅-5%）】 涨幅：327÷310-1=5.48%。投标单价低于基准价，按基准价算，已超过约定的风险系数，应 予调整。材料单价调整后为：308+310×(5.48%-5%)=309.50 元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]