[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939213":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939213,606,1,"单选题","某工程约定采用价格指数法调整合同价款，具体约定见表 7-11 数据，本期完成合同价款 为 1000 万元。计算应调整的合同价款差额为( )。 表 7-11 承包人提供材料和工程设备一览表(适用于价格指数调整方法)",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","115",false,{"key":16,"text":17,"correct":14},"B","125",{"key":19,"text":20,"correct":21},"C","116",true,{"key":23,"text":24,"correct":14},"D","126","应调整的合同价款=1000×[0.42+(0.13×120\u002F100+0.45×1200\u002F1000)-1]=116 万元。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]