[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939211":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939211,606,2,"多选题","编制建设工程项目费用计划时，常用的费用目标分解方式有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按投资构成分解",true,{"key":16,"text":17,"correct":18},"B","按承包方分解",false,{"key":20,"text":21,"correct":14},"C","按项目组成分解",{"key":23,"text":24,"correct":14},"D","按时间进度分解",{"key":26,"text":27,"correct":18},"E","按设计方分解","ACD","编制资金使用计划过程中最重要的步骤，就是项目投资目标的分解。投资目标的分 解可以分为按投资构成、按子项目、按时间分解三种类型。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]