[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939207":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939207,606,1,"单选题","《计价规范》规定，分部分项工程量清单应采用( )计价。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","综合单价",true,{"key":16,"text":17,"correct":18},"B","全费用综合单价",false,{"key":20,"text":21,"correct":18},"C","工料单价",{"key":23,"text":24,"correct":18},"D","部分费用综合单价","《计价规范》规定，分部分项工程量清单应采用综合单价计价。《建设工程造价咨询 规范》GB\u002FT 51095-2015，强调最高投标限价、投标报价的单价应采用全费用综合单价。本教材 主要依据《计价规范》编写，即采用综合单价法计价。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]