[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939203,606,1,"单选题","我国目前实行的工程量清单计价采用的综合单价是部分费用综合单价，清单项目单价中 不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","规费和税金",true,{"key":16,"text":17,"correct":18},"B","企业管理费、规费",false,{"key":20,"text":21,"correct":18},"C","规费、利润和税金",{"key":23,"text":24,"correct":18},"D","企业管理费、规费、利润和税金","我国目前实行的工程量清单计价采用的综合单价是部分费用综合单价，分部分项工 程、措施项目、其他项目单价中综合了人、料、机费用、管理费、利润，以及一定范围内的风险 费用，单价中未包括规费和税金，是不完全费用综合单价。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]