[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939198":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939198,606,2,"多选题","分部分项工程费=∑(分部分项工程量×综合单价)，其中综合单价不包括( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","税金",true,{"key":16,"text":17,"correct":14},"B","规费",{"key":19,"text":20,"correct":21},"C","企业管理费",false,{"key":23,"text":24,"correct":21},"D","利润",{"key":26,"text":27,"correct":21},"E","一定范围的风险费用","AB","综合单价包括人工费、材料费、施工机具使用费、企业管理费和利润以及一定范围 的风险费用。【注】建筑安装工程计价中的综合单价不包括规费和税金",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]