[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939182":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939182,606,2,"多选题","设备安装工程概算编制方法主要有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预算单价法",true,{"key":16,"text":17,"correct":18},"B","定额指标法",false,{"key":20,"text":21,"correct":14},"C","扩大单价法",{"key":23,"text":24,"correct":18},"D","工程量清单法",{"key":26,"text":27,"correct":14},"E","概算指标法","ACE","本题考查的是设备安装工程概算编制方法。设备安装工程概算编制方法有预算单价法、扩大单价法和概算指标法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]