[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939168":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939168,606,1,"单选题","工作项目铺底流动资金，一般按照流动资金的（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%",false,{"key":16,"text":17,"correct":14},"B","20%",{"key":19,"text":20,"correct":21},"C","30%",true,{"key":23,"text":24,"correct":14},"D","40%","本题考查的是工程项目总投资组成。铺底流动资金是指生产性工程项目为保证生产和经营正常进行，按规定应列入工程项目总投资的铺底流动资金，一般按流动资金的30%计算。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]