[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939164":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939164,606,2,"多选题","建筑安装工程直接费用中，措施费用主要包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","安全文明施工费",true,{"key":16,"text":17,"correct":14},"B","已完工程及设备保护费",{"key":19,"text":20,"correct":14},"C","二次搬运费",{"key":22,"text":23,"correct":24},"D","工程排污费",false,{"key":26,"text":27,"correct":24},"E","劳动保险费","ABC","本题考查的是措施项目费。措施项目费内容包括：（1）安全文明施工费。（2）夜间施工增加费。（3）二次搬运费。（4）冬雨季施工增加费。（5）已完工程及设备保护费。（6）工程定位复测费。（7）特殊地区施工增加费。（8）大型机械设备进出场及安拆费。（9）脚手架工程费。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]