[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939162":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939162,606,2,"多选题","某双代号网络计划如下图所示，图中存在的绘图错误有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个终点节点",false,{"key":16,"text":17,"correct":18},"B","节点编号重复",true,{"key":20,"text":21,"correct":18},"C","两项工作有相同的节点编号",{"key":23,"text":24,"correct":14},"D","循环回路",{"key":26,"text":27,"correct":14},"E","多个起点节点","BC","本题考查的是工作顺序安排。有两个⑦节点，JK 两项工作有相同的节点编号④⑧。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]