[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939157":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939157,606,1,"单选题","已知某建设工程网络计划中 A 工作的自由时差为 5 天，总时差为 7 天。监理工程师在检查施工进度时发现只有该工作实际进度拖延，且影响总工期 3 天，则该工作实际进度比计划进度拖延（）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":14},"C","8",{"key":22,"text":23,"correct":24},"D","10",true,"本题考查的是项目进度控制方法。该工作实际进度比计划进度拖延＝7＋3＝10（天）。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]