[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939155":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939155,606,2,"多选题","某工程双代号网络计划如下图，已标出各项工作的最早开始时间（ESi-j）、最迟开始时间（LSi\u0002j）和持续时间（Di-j）。该网络计划表明（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作 C 和工作 E 均为关键工作",true,{"key":16,"text":17,"correct":14},"B","工作 B 的总时差和自由时差相等",{"key":19,"text":20,"correct":21},"C","工作 D 的总时差和自由时差相等",false,{"key":23,"text":24,"correct":14},"D","工作 G 的总时差.自由时差分别为 2 天和 0 天",{"key":26,"text":27,"correct":14},"E","工作 J 的总时差和自由时差相等","ABDE","本题考查的是制定进度计划的方法。选项 A 错误，工作 C 不是关键工作。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]