[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939154":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939154,606,2,"多选题","针对下列双代号网络计划，下列表述正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作 A 的 FF 为 0 天",true,{"key":16,"text":17,"correct":18},"B","工作 E 的 FF 为第 4 天",false,{"key":20,"text":21,"correct":14},"C","工作 B 的 LF 为第 7 天",{"key":23,"text":24,"correct":18},"D","工作 E 的 LS 为第 7 天",{"key":26,"text":27,"correct":14},"E","工作 C 的 TF 为 2 天","ACE","本题考查的是制定进度计划的方法。本网络计划的计算工期为 17 天，关键线路为 ABDFG。选项 B，工作 E 的 FF 为 1；选项 D，工作 E 的 LS 为第 8 天。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]