[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939153":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939153,606,2,"多选题","下列关于双代号网络计划的表述，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","可能没有关键线路",false,{"key":16,"text":17,"correct":18},"B","至少有一条关键线路",true,{"key":20,"text":21,"correct":18},"C","在计划工期等于计算工期时，关键工作为总时差为零的工作",{"key":23,"text":24,"correct":14},"D","在网络计划执行过程中，关键线路不能转移",{"key":26,"text":27,"correct":14},"E","由关键节点组成的线路就是关键线路","BC","本题考查的是制定进度计划的方法。选项 A，正确的表述应为“一个网络计划可能有一条，或几条关键线路，不可能没有关键线路”；选项 D，正确的表述应为“在网络计划执行过程中，关键线路有可能转移”；选项 E，正确的表述应为“在双代号网络计划和单代号网络计划中，关键线路是总的工作持续时间最长的线路”。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]