[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939152":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939152,606,2,"多选题","S 形曲线比较法以横坐标表示时间，纵坐标表示累计完成任务量，通过实际进度与计划进度的比较，可以获得的信息有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","实际工程进展",true,{"key":16,"text":17,"correct":14},"B","进度超前或拖延的时间",{"key":19,"text":20,"correct":14},"C","工程量的完成情况",{"key":22,"text":23,"correct":14},"D","后续工程进度预测",{"key":25,"text":26,"correct":27},"E","进度计划是否合理",false,"ABCD","本题考查的是项目进度控制方法。S形曲线比较法中将项目进度基准计划的S形曲线和实际S形曲线绘制在同一张图上，可以得到项目实际进度比计划进度超前或拖后的时间，项目实际进度比计划进度超额或拖欠的工作量完成情况。另外，还能进行后续的进度预测。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]