[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939151":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939151,606,2,"多选题","下列关于工程费用与工期在一般情况下的关系，正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工期延长，工程总费用一定增加",false,{"key":16,"text":17,"correct":14},"B","工期缩短，工程总费用一定增加",{"key":19,"text":20,"correct":21},"C","工期缩短，直接费用随着增加",true,{"key":23,"text":24,"correct":14},"D","工期缩短，工程间接费用随着增加",{"key":26,"text":27,"correct":21},"E","工期延长，间接费用随着增加","CE","本题考查的是进度计划优化。工程总费用由直接费用和间接费用组成。直接费用由人工费、材料费、机械使用费、其他直接费用及现场经费等组成。施工方案不同，直接费用也就不同，如果施工方案一定，工期不同，直接费用也不同。直接费用会随着工期的缩短而增加。间接费用包括企业经营管理的全部费用，它一般会随着工期的缩短而减少。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]