[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939150":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939150,606,1,"单选题","某网络计划中，工作 M 的最早完成时间为第 8 天，最迟完成时间为第 13 天，工作的持续时间为 4 天，与所有紧后工作的间隔时间最小值为 2 天。则该工作的自由时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","4",{"key":23,"text":24,"correct":18},"D","5","本题考查的是制定进度计划的方法。工作 M 与所有的紧后工作的间隔时间最小值为 2 天，所以自由时差为 2 天。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]