[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},939149,606,1,"单选题","在不影响其紧后工作最早开始的前提下，工作可以利用的机动时间是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","总时差",false,{"key":16,"text":17,"correct":14},"B","闲置时间",{"key":19,"text":20,"correct":14},"C","最早时间",{"key":22,"text":23,"correct":24},"D","自由时差",true,"本题考查的是制定进度计划的方法。自由时差是指在不影响其紧后工作最早开始的前提下本工作可以利用的机动时间。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]