[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939148":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939148,606,1,"单选题","下列关于实际进度与计划进度的对比分析方法中，不属于趋势分析方法的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键路径法",true,{"key":16,"text":17,"correct":18},"B","列表比较法",false,{"key":20,"text":21,"correct":18},"C","前锋线比较法",{"key":23,"text":24,"correct":18},"D","横道图比较法","本题考查的是项目进度控制方法。实际进度与计划进度的对比分析方法有趋势分析、关键路径和挣值管理。趋势分析法包括横道图比较法、前锋线比较法、S 形曲线比较法、香蕉曲线比较法和列表比较法",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]