[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939147":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939147,606,1,"单选题","下列不属于在匀速进展横道图比较法中，完成任务量表示方法的为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用支出",false,{"key":16,"text":17,"correct":18},"B","合同清单量",true,{"key":20,"text":21,"correct":14},"C","劳动消耗量",{"key":23,"text":24,"correct":14},"D","实物工程量","本题考查的是项目进度控制方法。匀速进展横道图比较法是指在工程项目中每项工作在单位时间内完成的任务量相等，此时，每项工作累计完成的任务量与时间成线性关系，完成的任务量可以用实物工程量、劳动消耗量或费用支出表示，或用其物理量的百分比表示。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]