[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939146":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939146,606,1,"单选题","下列不属于进度计划控制的具体内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定进度是否已发生变化",false,{"key":16,"text":17,"correct":18},"B","对工期定额进行重新编制",true,{"key":20,"text":21,"correct":14},"C","对实际发生的变化实施管理",{"key":23,"text":24,"correct":14},"D","对造成进度变化的因素施加影响","本题考查的是项目进度控制的依据。进度计划控制的具体内容包括：对造成进度变化的因素施加影响，以保证这种变化朝着有利的方向发展；确定进度是否已发生变化；在变化实际发生时，对这种变化实施管理。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]