[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939145":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939145,606,2,"多选题","实际进度与计划进度对比分析的趋势分析包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","横道图比较法",true,{"key":16,"text":17,"correct":14},"B","前锋线比较法",{"key":19,"text":20,"correct":14},"C","S 形曲线比较法",{"key":22,"text":23,"correct":14},"D","香蕉曲线比较法",{"key":25,"text":26,"correct":27},"E","关键路径法",false,"ABCD","常用的进度比较方法有：趋势分析、关键路径法和挣值管理。(1)趋势分析。1)横 道图比较法。2)前锋线比较法。3)S 形曲线比较法。4)香蕉曲线比较法。5)列表比较法。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]