[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939143,606,1,"单选题","工程项目进度管理中，采用工期最短的资源优化方法的工作有：①检查每天资源需用量 是否超过资源限量；②计算网络计划每天资源需用量；③对资源冲突的工作重新安排顺序；④重 复以上步骤直到出现优化方案。正确的实施顺序是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①→②→③→④",false,{"key":16,"text":17,"correct":18},"B","②→①→③→④",true,{"key":20,"text":21,"correct":14},"C","①→③→②→④",{"key":23,"text":24,"correct":14},"D","②→③→①→④","资源有限——工期最短的优化调整步骤如下： (1)计算网络计划每天资源需用量； (2)从计划开始日期起，逐日检查每天资源需用量； (3)调整网络计划。对资源冲突的诸项工作做新的顺序安排。 (4)重复以上步骤，直至出现优化方案为止。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]