[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939141":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},939141,606,1,"单选题","工期优化选择应缩短持续时间的关键工作不考虑( )因素。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","有充足备用资源的工作",false,{"key":16,"text":17,"correct":14},"B","缩短持续时间增加费用最少的工作",{"key":19,"text":20,"correct":21},"C","总时差的大小",true,{"key":23,"text":24,"correct":14},"D","缩短持续时间对质量和安全影响不大的工作","选择应缩短持续时间的关键工作应考虑下列因素： 1)缩短持续时间对质量和安全影响不大的工作； 2)有充足备用资源的工作； 3)缩短持续时间增加费用最少的工作。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]