[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939139":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939139,606,1,"单选题","利用定额进行时间估算一般采用( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专家估算法",false,{"key":16,"text":17,"correct":18},"B","单一时间估算法",true,{"key":20,"text":21,"correct":14},"C","三时估算法",{"key":23,"text":24,"correct":14},"D","蒙特卡罗分析法","类比估算法也是一种专家估算法。利用定额进行时间估算一般采用单一时间估算法。 专家判断估算常常采用三时估算法。模拟法最常用的是蒙特卡罗分析法。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]