[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939138":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939138,606,2,"多选题","下列关于双代号绘图法的表述，正确的是( )。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","在双代号网络图中，工作由一根箭线连接两个圈表示",true,{"key":16,"text":17,"correct":14},"B","工作名称写在箭线的上面，完成工程需要的时间写在箭线的下面",{"key":19,"text":20,"correct":21},"C","箭头表示工作的开始，箭尾表示工作的结束",false,{"key":23,"text":24,"correct":14},"D","不消耗时间和资源的工作用虚箭线表示",{"key":26,"text":27,"correct":14},"E","需要消耗时间和资源的工作用实箭线表示","ABDE","C.箭头表示工作的结束，箭尾表示工作的开始。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]