[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939137":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939137,606,2,"多选题","某分部工程双代号时标网络计划如图所示，关键工作有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作 A",true,{"key":16,"text":17,"correct":18},"B","工作 B",false,{"key":20,"text":21,"correct":14},"C","工作 C",{"key":23,"text":24,"correct":18},"D","工作 E",{"key":26,"text":27,"correct":14},"E","工作 F","ACE","无波形线的线路为关键线路。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]