[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939133":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939133,606,2,"多选题","工作顺序安排的依据包括( )。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","进度管理计划",true,{"key":16,"text":17,"correct":14},"B","成果说明文件",{"key":19,"text":20,"correct":14},"C","各项工作之间的逻辑关系",{"key":22,"text":23,"correct":14},"D","组织过程资产",{"key":25,"text":26,"correct":27},"E","成本强度",false,"ABCD","工作顺序安排的依据：(1)进度管理计划。(2)工作清单。(3)工作属性。(4)里程碑 清单。(5)项目范围说明书。(6)环境因素。(7)组织过程资产。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]