[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939129":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939129,606,2,"多选题","下列不属于工程项目进度管理的工作过程的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作定义",false,{"key":16,"text":17,"correct":18},"B","工作内容实施",true,{"key":20,"text":21,"correct":14},"C","进度计划制定",{"key":23,"text":24,"correct":14},"D","进度控制",{"key":26,"text":27,"correct":18},"E","成本计划修改","BE","本题考查的是工程项目进度管理的工作过程。进度管理包括为确保项目按期完成所必须的所有过程，包括规划进度管理、工作定义、工作顺序安排、工作资源估算、工作时间估算、进度计划和进度控制等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]