[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939128":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939128,606,2,"多选题","工作进度计划中，需要更新的项目文件包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","风险登记册",true,{"key":16,"text":17,"correct":18},"B","工作时间",false,{"key":20,"text":21,"correct":18},"C","工作态度",{"key":23,"text":24,"correct":14},"D","工作属性",{"key":26,"text":27,"correct":14},"E","日历","ADE","本题考查的是工作资源估算。工作进度计划中项目文件更新，需要更新的项目文件包括：（1）工作资源需求：资源平衡可能对所需资源类型与数量的初步估算产生影响，因而需要对工作资源需求进行更新；（2）工作属性：制定进度计划过程中可能改变了资源需求和其他相关内容，需要对相应的工作属性进行更新；（3）日历；（4）风险登记册：需要更新风险登记册以反映进度假设条件所隐含的机会或威胁。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]