[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939126":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939126,606,2,"多选题","某分部工程双代号网络图如下图所示，图中错误有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","多个起点节点",false,{"key":16,"text":17,"correct":18},"B","多个终点节点",true,{"key":20,"text":21,"correct":14},"C","工作代号重复",{"key":23,"text":24,"correct":18},"D","节点编号有误",{"key":26,"text":27,"correct":14},"E","存在循环网路","BD","本题考查的是工作顺序安排。有⑦⑧两个终点节点。虚工作③②箭头的节点编号数字小于箭尾节点编号的数字。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]