[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939125":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},939125,606,2,"多选题","项目管理计划中需要更新的内容包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进度基准",true,{"key":16,"text":17,"correct":18},"B","成本数据",false,{"key":20,"text":21,"correct":14},"C","进度管理计划",{"key":23,"text":24,"correct":14},"D","成本基准",{"key":26,"text":27,"correct":18},"E","项目成本计划","ACD","本题考查的是项目进度控制的工作成果。项目管理计划中需要更新的内容包括进度基准、进度管理计划以及成本基准等。需要更新的项目文件包括进度数据、项目进度计划和风险登记册等。",{"id":6,"name":31,"category":32,"favorite":33},"工程项目组织与管理","建筑工程",0]