[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939124":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},939124,606,1,"单选题","某双代号网络图如下图所示，单位（天），其计算工期为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":18},"B","17",true,{"key":20,"text":21,"correct":14},"C","16",{"key":23,"text":24,"correct":14},"D","21","本题考查的是制定进度计划的方法。关键线路为 B-C-F-G，其持续时间之和为 2+5+6+4=17天。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]