[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-939121":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},939121,606,1,"单选题","下列关于关键工作和关键线路的表述，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路上的工作全部是关键工作",true,{"key":16,"text":17,"correct":18},"B","关键工作不能在非关键线路上",false,{"key":20,"text":21,"correct":18},"C","关键线路上不允许出现虚工作",{"key":23,"text":24,"correct":18},"D","关键线路上的工作总时差均为零","本题考查的是制定进度计划的方法。选项 B 非关键线路上也有可能有关键工作；选项 C 关键线路上允许有虚工作；选项 D 应为“总时差为零的工作为关键工作”。",{"id":6,"name":27,"category":28,"favorite":29},"工程项目组织与管理","建筑工程",0]